Tag: Featured Content

RES says, ‘…people [will] become accustomed to the development.’

Since our last post the SSAG has been able to read the entire Response to Submissions (RTS) as have many other members of the community. We all seem to be in agreeance about the sufficiency of the RTS. It beggars belief that it has taken almost two years to lodge this document which is basically just a rehash of the EIS, and devoid of any consideration of the community issues, despite RES’s claim: …’The issues raised in each submission were then extracted, summarised, and collated … and responses have been provided that are proportionate to the relevance of the issue.’ Clearly the responses are based on RES’s point of view, not ours!

RES’s whole attitude towards this community’s concerns about visual impacts can be summed up by a comment in the Land Use Conflict Risk Assessment in the RTS which says: ‘This potential conflict is however expected to ease over time as screening vegetation matures and people become accustomed to the development.’

RES confirmed what we suspected all along that Renew Estate (Renew) were not genuine about developing the project. They were expecting that there would be minimal opposition and approval would be straightforward. We believe it is no coincidence that once Renew saw how strong the community opposition was to the project it became too hard to deal with, so was ‘put on holdat the end of 2018. RES stated this on 7 April 2020 when they informed us that they were the new developers and again in the first paragraph of the RTS.

Renew repeatedly told the Department of Planning, Industry and Environment (DPIE) who in turn told the SSAG that Renew still had to finalise some ‘additional archaeological studies’ before the RTS could be lodged. Interestingly the RTS contained no ‘additional archaeological studies’ and makes reference to an agreement between the Department and AECOM (the consultant who prepared the EIS/RTS) in December 2018 relating to these studies. The SSAG is seeking clarification from the DPIE on the contents of the agreement. What is deplorable is the degree of anguish this unnecessary delay has caused the Sutton community, and to add insult to injury, Renew just passed it on like a ‘hot potato‘.

In a previous post we mentioned that we had written to Minister Stokes again, asking for an opportunity to put forward updates on the issues that the Sutton community had included in their submissions.

On 26 June 2020, representatives from the SSAG had the opportunity to do so by participating in a teleconference with the Executive Director of the DPIE and other DPIE representatives.

In preparation for this meeting the SSAG read all the submissions from Sutton residents and compiled a list of the issues raised so that we would have an understanding of what this community considers important. Overall there are 43 issues which were then grouped into 5 topic areas. In order there is 1. Traffic/road safety (incl the heavy vehicle route), 2. Visual impacts 3. Site suitability 4. Biodiversity 5. Socio-economic impacts.

Here is a very brief summary of the information the SSAG shared with the DPIE in response to the RTS:

1. Traffic/road safety – the proposed mitigation to deal with the increased traffic is farcical, aspirational and is in no way enforceable. SSAG traffic survey shows a very different scenario to that of the EIS.

2. Visual impacts – developers were requested to expand the visual impact studies, they added just two more properties, no more. The RTS included an additional measure to mitigate visual impacts, which is, if it can’t be mitigated at the source, it may be reduced at the ‘receptor’. Hands up those who would like a barrier put on your property to hide the ugliness? This is preposterous and would be a nightmare to implement let alone maintain.

3. Site suitability – The SSAG reiterated that the proposed development is not compatible with any of the planning strategies for the area and also reminded the DPIE that the Office of Environment and Heritage stated this area is critical to maintain biodiversity connections between Mulligans Flat Nature Reserve and Goorooyarroo with other regions of NSW.

Inconsistent with the NSW proposed renewable energy zones (REZ’s). Technically a solar facility will generate energy anywhere the sun shines, but that doesn’t mean they should be put just anywhere. There are many factors that determine the best locations for large-scale renewable energy generation, and this area is not one of them. A number of different studies have been conducted over the past decade and have consistently shown the same three (3) regions which are the New England, Central West and South West as the better areas for large-scale renewable energy (both wind and solar) generation in NSW.

On 17 December 2010, AECOM provided the NSW Department of Environment, Climate Change and Water (DECCW) with their ‘Pre-feasibility Study for a Solar Power Precinct.’ One objective of the study was to: …’Determine the feasibility of large scale solar projects in NSW and to test the concept that the co-location of solar plants into a precinct to facilitate sharing of infrastructure may expedite financial viability.‘…

16 locations across NSW were chosen for the study and five (5) areas which includes the three (3) regions above were chosen for further studies.  One of the 16 was the Lake George region which is only 14 kms to the east and was ranked 15th for three (3) different types of PV technology, and 16th for generation potential. What does that say? There are far better areas of NSW for large-scale solar energy generation, despite the claims that AECOM made in the EIS ‘this region has among the best resources in the world‘.

If AECOM knew all this information as far back as 2010 why didn’t they advise their client Renew that there were much better locations for large-scale solar development such as the areas identified by them in their report. These same areas have subsequently been supported by the NSW Government’s submissions to AEMO’s 2018 ISP and by DNV-GL who also provided advice to AEMO for the 2018 ISP. In May of this year the DPIE called for registrations of interest in the ‘pilot’ Central West REZ.

4. Biodiversity – There are both NSW and Commonwealth guidelines to determine if a development will have a significant impact (SI) on threatened species. The Springdale Biodiversity Assessment Report (BDAR) for the Golden Sun Moth doesn’t meet either of these SI guidelines.

Included in these SI guidelines there is also a threshold at which it has been determined that there will be a SI, the BDAR exceeds the impact thresholds for the Golden Sun Moth. Why have these guidelines if they aren’t going to be applied?

These same SI guidelines state that it is not enough just to have mitigation. Only mitigation measures that have proven to be successful in similar situations should be considered. There is not one proven mitigation measure included in the EIS/RTS. Again, why have the guidelines if they aren’t going to be used. Little wonder Australia is facing a faunal extinction crisis!

5. Socio-economic – The spatial and economic distributive inequity of this project. The economic benefits will go to RES and just one landholder who live geographically distant from the project and will not to be impacted. Whereas those living in closest proximity to the proposed development will bear the full impact for 35 years and will not receive any economic benefit.

A community fund of $100,000 has been proposed. If you break that down by population of the area over the proposed lifespan of the project this is what the developer thinks is adequate consideration for each person:
$100,000/1660 (ABS pop) = $60.24 each
OR $1.72 each year for 35 years
whereas,
According to the LDC Infrastructure website, ‘Solar lease rates are almost always based on both the quality and quantity of the land assigned to the lease.
On average, solar rental fees will fall somewhere around $700-$3000 an acre.’ https://ldcinfrastructure.com.au/company/
Based on the approximately 850 acre Springdale site the landholder stands to make potentially many millions of dollars.

Like everyone in the community the SSAG is waiting on the DPIE to complete their assessment of the Springdale project which is then provided to the Independent Planning Commission who will conduct hearings (another opportunity for the community to voice their objections) before making the final determination on the Springdale project.



Response document comments misleading

The SSAG is concerned that some members of the community are becoming anxious about comments in the Springdale Response to Submissions (RTS). Hopefully, we can shed some light on these comments to dispel the fears that the RTS has created.

It’s important to bear in mind that the consultants that prepared the EIS and RTS are working for the developer.

These are just two of the issues that have come to our notice so far.

Firstly, on page 31 it states, ‘Given that more submissions were received in support than in objection, the proponent believes there is significant community support for the Project.’

This comment is misleading.

The determination of a project is not based on the most number of supporters or objectors.

The submissions for this project came from not only the local area but also other regions of NSW, as well as interstate. SSAG sought clarification from the DPIE on how submissions are evaluated. While the DPIE reviews every submission, more weight is given to the issues raised in submissions from the local community.

Based on the submissions lodged, there was only three (3) Sutton residents that supported the development, which refutes the claim of ‘significant community support’.

The other is on page 1, which states, A total of 239 submissions were received by DPIE including four duplicates’.

The below image is taken from the DPIE website which shows there was a total of 247 submissions lodged for the project.  Removal of the four (4) duplicate leaves 243 submissions, not 239.

Source: DPIE Major Projects site Springdale 8073

While the community doesn’t get an opportunity to formally respond to the Springdale RTS, the SSAG will continue to review the document and will be compiling a list of all the issues we believe should be made known to the DPIE for taking into consideration in the assessment process.  

If you find anything that you believe should be added to our list please send us an email contact@suttonsolaractiongroup.com.

If there is anything that is causing you concern please contact the SSAG so we may assist.

Response to Submissions for Springdale has finally been lodged.

Well it does exist. The Response to Submissions (RTS) has finally been lodged with the Department of Planning, Industry and Environment (DPIE). The RTS is 471 pages, so another epic document produced by AECOM.

After a cursory quick browse there are a few things that stand out, so closer inspection should be ‘enlightening’.

The first thing you will notice is that AECOM gave this document to Renew Estate on 25 October 2018, so as we suspected they sat on this till they could off-load the project.

The SSAG has said all along that Renew Estate was misleading the community and the DPIE for well over 18 months about the delay to the RTS. The delay was supposedly due to ‘further archaeological studies‘ being finalised. The RTS does not contain any ‘further archaeological salvage program‘ information that we can find. Perhaps it is still being finalised!

On the same topic, on page 114 it mentions that … ‘The proponent has undergone consultation with DPIE to discuss timing of the archaeological
salvage program… see letter to DPIE attached in Appendix D
). There is no letter to DPIE that appears in Appendix D about this issue.

We would certainly welcome feedback from anyone on anything they uncover in the RTS, just to make sure nothing is missed. As the author of both the EIS and RTS are the same, we are sure there will be plenty to find.

Below is the link to the DPIE Springdale page. Then click on Response to Submissions and there is also the Amendment Report.

https://www.planningportal.nsw.gov.au/major-projects/project/9756

RES-Group has five more days to lodge the Response to Submissions (RTS) for the Springdale development

As reported in our last post the Department of Planning, Industry and Environment (DPIE) gave the RES-Group (RES) until the end of May to lodge the RTS for the Springdale development.

On 31 May 2020 it will have been 21 months and 2 days or 641 days since submissions closed for the Springdale project.

Following our last post one member of our group emailed RES to express how they feel about the change of developer (see below for copy of email). The sentiments expressed in the email are shared by many others in the community.

The SSAG are eagerly awaiting the public release of the long-anticipated RTS to see how Renew Estate/RES-Group have responded to all of the concerns raised in submissions, especially since it has taken them so long to finalise this document.

The SSAG will contact the DPIE early next week to see if the ‘elusive’ Springdale RTS has been lodged. We will keep you informed.

Renew who??

On 7 April 2020 some of you may have received an email from Stephen Reid informing you that the company he works for, the RES-Group, has …’acquired the development assets of the Springdale Solar Farm‘…, which, given that this project hasn’t even provided a Response to Submission, we expect this means they have ‘acquired’ a lot of papers i.e EIS documents and anything that goes with that.

Mr Reid’s letter had this to say. …”As Renew Estate moves away from the project, please be assured that they have delivered a complete handover of all material to us, so that we can properly stand in their shoes as developer going forward. Rosie has taken us through all of the details as to the various discussions, emails and meetings with all stakeholders, especially the community.”… Well, that handover would’ve been short, bearing in mind Renew Estate has ignored this community since August 2018. See link below.

Given that Mr Reid’s email came just 6 days after our meeting with Minister Stokes the SSAG has been back in touch with our local member, Ms Wendy Tuckerman MP to share this information and ask her for her support. We have asked her to consider a number of courses of action on behalf of the SSAG which she has agreed to do. We will keep the community informed via posts on our website.

Whilst the developers name may have changed, the multitude of issues that the community identified in the EIS has not. The SSAG is not being distracted by this latest twist, our focus continues to be on showing just how unsuitable the proposed Springdale solar development is to this area.

SSAG meets with Hon. Rob Stokes MP, Minister for Planning and Public Spaces

You will be aware that we haven’t posted anything since January 2020. During this time SSAG representatives have met with our local member Ms Wendy Tuckerman who was very sympathetic to our dilema and made this meeting with the Minister possible. We are very grateful for her making this happen, especially because it is not everyday you get an opportunity to speak directly to a Minister.

Given we are currently under COVID-19 conditions our meeting was conducted by a teleconference. Other participants were Ms Tuckerman and her advisor, a senior official from the Department of Planning, Industry and Environment, and a senior member of Minister Stokes office. SSAG was represented by Jacqui Hassall, Mark and Dianne Burgess.

The SSAG presented the Minister with a detailed document outlining a range of issues, in particular, the favourable treatment Renew Estate Estate appears to be receiving from the DPIE.  We were able to point out that the 10 other recent large-scale solar projects in NSW had been given between 18 and 52 days to respond to any community objections, however as of 1 April, 2020, Renew Estate Estate has had 581 days to respond to our community’s objections and still nothing.   

Our document pointed out that Renew Estate has previously told the DPIE that they would provide their response by the end of January 2019 and then it was they would provide it by the end of November 2019.  It’s now April 2020 and they have still has not lodged their response nor have they provided any reason as to why it’s been delayed. 

The Minister appeared genuinely shocked that this process has been allowed to drag on for so long and apologised to the SSAG for the DPIE allowing it to happen.

The senior DPIE representative offered to visit the site immediately once travel restrictions due to the corona virus are lifted.  We welcomed his offer and look forward to be able to visit the site with him and take his through all the concerns that have been raised by the local community.  He indicated that the DPIE had corresponded with Renew Estate since the close of objections, many of which he said have gone unanswered.

The Minister was also highly complementary of the document we provided him for the meeting.

The SSAG is hopeful that we may be soon able to get this issue resolved.

We will keep the community updated with developments through the SSAG website. 

Renew Estate fails to lodge the Response to Submissions and whats next ?

Why has the Response to Submission (RTS) phase of the Springdale Solar project been allowed to drag on for so long without any valid reasons or evidence being shown by Renew Estate that explains what the hold up is?

The SSAG’s has been attempting to find out about the RTS for over 12 months and the latest communication from DPIE has now suggested a possible course of action for the New Year. But before we share that with you, here is the list of communications between the SSAG and the DPIE.

The Springdale EIS public exhibition period opened on 18 July 2018, and closed on 29 August 2018.

  • 5 December 2018, 98 days after close of submissions SSAG contacted DPIE re the RTS
  • DPE responded and said Renew Estate had contacted the Department a week or so ago and said that Renew Estate would not get back to DPE before Christmas. DPE indicated Renew Estate would likely respond with the RTS towards the end of January 2019 as they were still working on the additional archaeological survey work.
  • 24 January 2019, 148 days post close of submissions
    Second time SSAG contacted DPE about progress of the RTS
  • 29 January 2019, DPE responded and said Renew Estate was still preparing the RTS
  • 11 April 2019, 225 days post close of submissions
    Third time SSAG contacted DPE about progress of the RTS
  • DPE responded and SSAG was told, the DPE would not be contacting Renew Estate and that Renew Estate was still working on the additional archaeological survey. DPE also said the SSAG could contact Renew Estate if we wanted more information.
  • 4 October 2019, 401 days post close of submissions
    Fourth time SSAG contacted DPIE about progress of the RTS
  • 24 October 2019, DPIE contacted SSAG and informed us they had contacted Renew Estate and the completion of additional archaeological survey was the reason for the delay of the RTS. Renew Estate advised the DPIE that the RTS would be provided by late November 2019.
    DPIE also emphasised the importance of keeping the community informed and requested that Renew Estate provide an update on the project to the community.
  • 4 December 2019, 462 days post close of submissions
    Fifth time SSAG contacted DPIE about progress of the RTS
    SSAG also asked the DPIE what happens next if Renew Estate doesn’t lodge the RTS?
  • 19 December 2019, DPIE responded and informed the SSAG that the RTS HAD NOT been lodged.
    DPIE also informed the SSAG that they had been in contact with Renew Estate and reiterated the importance of keeping the community updated. Renew Estate advised the DPIE that a project update would be provided before the end of year.
    DPIE also stated they will consider the next steps in the new year, including finalising the assessment of the project in the absence of receiving a RTS or any material updates on the status of the project.
  • 20 December 2019, 478 days post close of submissions
    Sixth time SSAG contacted the DPIE about progress of the RTS
    The SSAG acknowledged the possible finalisation of the project as indicated by DPIE as both reasonable and appropriate given the circumstances.
    The SSAG also stated that a review of the DPIE Major Projects showed that the average timeframe for assessing the 41 solar developments approved since 2010 was 138 days (from close of submissions to determination). As of 5 January 2020, it is 494 days since submissions closed for the Springdale solar project, and the RTS hasn’t even been lodged. THIS IS 356 DAYS ABOVE THE DPIE AVERAGE.
  • 23 December 2019, Renew Estate emailed only seven people, NOT the community, with this message:
    ” We wanted to let you know that Renew Estate has been continuing to progress the development of the Springdale solar farm and the other projects we are developing in NSW.  

    We remain committed to the development of the Springdale Solar Farm. Together, with our partners we expect to complete the project’s additional planning studies in early 2020.

    We anticipate being able to make further detailed announcements on the development pathway for the project in the new year...”

This is Renew Estate’s idea of a project update. After 16 months this is all they offered. Do they expect the seven people they emailed to act as a spokesperson for their company? This just shows Renew Estate’s continued contempt for our community .

The completion of additional archaeological studies was used as the reason for the delay of the RTS in December 2018, April 2019 and again in October 2019. While the SSAG encourages thorough assessment practices, surely if an additional 10 months has not helped finalise these studies then Renew Estate should be explaining to DPIE why not.

Bearing in mind that the additional archaeological studies is only one issue that required a response, what about the numerous other issues that also require responses? What is the status of those?

Having said that, the SSAG doesn’t know what all the issues are? We expect that as part of the assessment process a summary of all issues raised in submissions would have been collated by the DPIE, otherwise how would they know if Renew Estate has addressed all the issues raised?

The SSAG has also discovered that the DPIE has now issued formal respond to submission requests to two solar project developers. One of those, the Jindera project where submissions closed on 13 November 2019, received 117 submissions, of those 106 were from the general public. This developer has been given 52 days to provide a RTS. See link below: https://www.planningportal.nsw.gov.au/major-projects/project/9811

In light of this new discovery the SSAG firmly believes our community is not being unreasonable in asking the DPIE to bring about a solution to the uncertainty of the RTS for the Springdale solar project. Renew Estate has already had 494 days in which to respond.

The SSAG has also been liaising with our Local Member, Wendy Tuckerman MP about our ongoing struggle, and the SSAG will be meeting with her on 10 February 2019.

The SSAG continues to work for the community and will keep you posted of any new developments.

Another uncertain Christmas

As reported in our last post and also the latest edition of the Sutton Chatter, Renew Estate had committed to lodge their Response to Submissions (RTS) by late November 2019.

On 4 December the SSAG (see email below) again wrote to the Department of Planning, Industry and Environment (DPIE) seeking answers to two simple questions:

1. Did Renew Estate lodge the RTS as stated?
OR
2. If they didn’t, then what happens now?

At the time of writing this post, 15 December 2019, the DPIE has not responded to the SSAG. This information vacuum is agonising for the community especially with the holiday season fast approaching. The questions are not complex, either the RTS has been submitted or it has not. As the impacted community surely we have a right to know what’s going on.

Despite DPIE’s request that Renew Estate engage with our community, they have failed to do so. This inaction displays an arrogant contempt by the developer.

We also advised in the December Chatter of a number of media articles relating to Renew Estate’s partner Wirsol and the Springdale solar project. A copy of those are also attached for your information.

Inquiry into sustainability of energy supply and resources in NSW

The SSAG wrote to the Committee Manager asking if we could be notified of progress relating to this inquiry, and also as a regional community impacted by a renewable energy development that we would like to host a hearing. Their response, all communications regarding the inquiry will be done via Twitter, and that until Parliament resumes in the New Year nothing will happen. The first sitting day for the NSW Legislative Assembly (NSW LA) is 4 February 2020. The SSAG provided a response expressing our concerns that Twitter is not a suitable communication tool for everyone. However, the SSAG will monitor Twitter and engage with the NSW LA again in the New Year. SSAG’s link below.

Last edition of Sutton Chatter for 2019

The upside of this waiting game has been that the SSAG has been able to dissect the Environmental Impact Statement (EIS) and research each topic and provide the community with bite size pieces of information that are easy to understand and gives more weight to our objections. We hope that members of our community have taken the time to read our monthly Sutton Chatter articles and have found them to be both informational and educational. See SSAG’s latest article.

Keep informed
With the next edition of the Sutton Chatter not till February 2020 the SSAG will keep the website up to date and should there be any updates we will notify you by way of emails (for those subscribed to our website). So if you don’t already subscribe you can follow the link on our homepage to sign up for notifications.

Thank you
For the vast majority of the community the public information session held on 7 December 2017 was the first time they had heard about this proposed development. If you take a look at the First Newsletter (see link), Renew Estate had expected the development to be operational by mid 2019. https://suttonsolaractiongroup.com/wp-content/uploads/2019/12/359de-springdale-solar-farm-newsletter-1-web.pdf

Its been two years since that initial contact and Renew Estate has been in the wind since August 2018. The SSAG strongly believes that the developers behind the proposed Springdale development thought our community would be an easy mark and we could be steamrolled. On the contrary, the SSAG has and will continue to campaign for this development not to be approved based on how completely unsuitable this area is and how inadequate the EIS has been in providing a credible assessment of the site and our area.

The SSAG would like to thank all our supporters and even though at times it may seem like nothing is happening we ask that you hang in there. When the time comes we will be looking for you to stand with us to show how strong our resolve is.

The SSAG would like to take this opportunity to wish everyone a safe and happy Christmas and New Year.

Springdale Solar SSD-8073 is 167 days over the Department of Planning, Industry and Environment’s own benchmark for assessing State Significant Development (SSD)

As we reported in the November edition of the Sutton Chatter (see link below) the Department of Planning, Industry and Environment (DPIE) provided a response to SSAG’s letter of October 4, 2019 (see below).

In short for those who haven’t had a chance to read the Chatter, DPIE advised they are aware of the high level of community interest in this project and that DPIE had been in contact with Renew Estate who advised the Response to Submissions Report “will be provided by late November 2019“. SSAG will be notified if this document is lodged and in turn SSAG will notify the community.

DPIE also reminded Renew Estate of the importance of keeping the community informed on the progress of the project and requested it update the local community on the status of the project. DPIE further advised SSAG they “will follow up further the community’s concern that these updates have not been provided“.

It is November 23 and Renew Estate has not contacted anyone nor have they added any new information on the project website. To refresh your memory their last Newsletter was dated August 2018. The first three Newsletters were listed in their News section and the last two were found in another part of the website, in you were looking for them follow this link: https://www.springdalesolarfarm.com.au/project-documents

What wasn’t in DPIE’s response was any kind of acknowledgement or apology about how poorly this project is tracking against DPIE’s own internal benchmarks. Since the close of submissions on 29 Aug 2018, 451 calendar days or 316 work days have passed. DPIE’s own benchmark for assessing State Significant Development’s is 149 days, (doesn’t say whether this is work days or calendar days). Assuming it is work days this project is now 167 days over their own benchmark, almost half a years deviation!!

It will be interesting to see if the DPIE actually do anything about Renew Estate’s lack of community engagement, especially as the developers are not penalised for poor community engagement. (see attached copy of DPIE response below)

Inquiry into sustainability of energy supply and resources in NSW

Almost 250 submissions (including SSAG’s, see last Post for link) were received in response to the inquiry, including community groups, local councils, the NSW Government, energy companies, trade unions, and individuals.

Notably Renew Estate was not listed as having provided a submission, however, their partner company Energy Estate’s submission (see link below) was promoting hydrogen in the Hunter Valley. https://www.parliament.nsw.gov.au/ladocs/submissions/65653/Submission%20-%20240.pdf

In a Media Release dated 24 October 2019 (see link below), Alex Greenwich MP, Committee Chair said “To get this right, we have to hear directly from the people who will experience the most significant impacts of any change. This means understanding any concerns, and making sure communities are supported in a way that serves them and their local economy and environment best”.
https://www.parliament.nsw.gov.au/ladocs/other/12725/Inquiry%20update%20-%20sustainability%20of%20energy%20supply%20and%20resources%20in%20NSW.pdf

Site visits and public hearings, including locations and dates, will be announced on the Committee’s webpage. https://www.parliament.nsw.gov.au/committees/inquiries/Pages/inquiry-details.aspx?pk=2542#tab-hearingsandtranscripts

SSAG will follow this with interest to see where and when these will be held. At the time of posting there are none scheduled. SSAG will be pushing for one to be held here.

If you are interested in reading some of the submissions here is the link: https://www.parliament.nsw.gov.au/committees/inquiries/Pages/inquiry-details.aspx?pk=2542#tab-submissions

Large-Scale Solar Energy Forums Outcomes

Who says persistence doesn’t pay off? The SSAG has finally tracked down the elusive ‘Outcomes’ document for the three forums (Armidale, Dubbo and Wagga Wagga) held earlier this year. DPIE’s response to SSAG on 24 October advised that the ‘Action Plan’, as it is known as, is being finalised by the Department of Planning, Industry and Environment and SSAG will be notified when it is publicly available.

Presentations for the three forums are available on the DPIE website:
https://www.planning.nsw.gov.au/Policy-and-Legislation/Renewable-Energy/Large-scale-Solar-Energy-Guideline

SSAG also notes that in 10 days time it will be six (6) months since the last forum was held in Wagga Wagga which SSAG representatives attended.

Independent Planning Commission (IPC Review)

You may be aware that Rob Stokes, Minister for Planning of Public Spaces has requested the Productivity Commissioner conduct a review of the Independent Planning Commission (IPC) following some controversies around recent IPC decisions. A report of the review is expected back to the Minister by mid-December 2019.  The Terms of Reference for the Review are available here: http://productivity.nsw.gov.au/ipc-review

SSAG will also follow this inquiry.

Latest Edition of the Sutton Chatter

SSAG’s submission to NSW Inquiry, Email to Department of Planning, Industry and the Environment, latest Sutton Chatter article

Its been a busy time since our last post, check out what’s been happening.

SSAG’s submission to the NSW Legislative Assembly Committee on Energy and Planning
You will recall we informed the group about the above inquiry which was looking at the sustainability of renewable energy in NSW which also included looking at how this impacts on regional communities. It is now available on the Inquiry webpage, we urge you to have a read of not only SSAG’s, but some of the other submissions to get an understanding of what the tone of this inquiry will be about. SSAG will be watching with interest to see where hearings are held, will they be in regional areas, west of the Great Divide or will they be in cities on the coast?

https://www.parliament.nsw.gov.au/ladocs/submissions/65529/Submission%20-%20187.pdf

Correspondence with the Department of Planning, Industry and the Environment (DPIE) and Renew Estate
Most of you would be unaware that the SSAG does contact the DPIE from time to time seeking updates on the progress of the Springdale project. We have reported previously that the DPIE doesn’t think it appropriate for them to contact Renew Estate and even suggested that we could contact them ourselves if we want to know anything. The attached copy of our latest email emphatically states that we believe it falls to DPIE to fulfil this duty on behalf of those impacted by developments.

Check out the latest Sutton Chatter article – Mitigation and Management Strategies how credible are they? See what we’ve uncovered…